main contractor : Sama Abha
Establishment of housing units in Aseer region
duration of contract : one year
|
|
The main contractor The group of the Establishment Abdul Rahman Al-Turky (ATCO)
Owner misery of high education
Typeofwork * Level and Filling. * Sub base layer. * Base
12 month contract period to one year, 2005 AD.
|
|
The main contractor Sama Abha establishment
Owner Abdalah Said Alahmary
Type of work * Levelling the area of the warehouse for the Establishment of 173000 m2
* Supply sand with spreading and pressing. * Supply sub base with spreading and pressing.
the duration of the contract is 60 days, 2007 AD.
|
|
The main contractor Sama Abha establishment Owner Baashen Company for Concrete Type of work * Levelling and filling. * Sub base layer. * 23400 m3. the duration of the contract is 60 days, 2007 AD.
|
|
The main contractor Sama Abha establishment
Owner Misfer Al-Shahrany, Establishment
Type of work * Levelling and filling. * Sub base layer. * 140000 m3
the duration of the contract is 45 days, 2007 AD.
|
|
The main contractor Turkish company vimco
Owner minestery of high education
Type of work * Filling. * Building roads. * Supply of 2500000 m3 Sand.
B - Al Rashid Trading & Contracting Co.
* Supply of 115000 m 3 of sand.
the duration of the contract is 18 months, subcontract in 2004
|
|
Themaincontractor Contracting systems Establishment
OwnerMinistryofwater
Type of work * Establishing the civil work for the stations.
* Extending pipelines in various sizes
the duration of the contract is 8 months, 2004 AD
|
|
The main contractor Al-Mous Establishment
Owner Al-Mous Establishment
Type of work * Materials Supply. * 500000 m3 of sand.
the duration of the contract is 6 months, 2005 AD.
|
|
Themaincontractor Mohammed A-Habib Company
Owner A-Habib Company
Type of work * a Part of finishing
the duration of the contract is 6 months .2006 AD.
|
|
main contractor Eastern for Trading and Contracting,
Owner Aramco Eastern for Trading and Contracting
Type of work * Spray and protection of the roads side for petrol pipes at Aramco.
the duration of the contract is 60 days, 2004 AD
|
|
The main contractor Chinese company & Al-Sowekit
Owner raill way co-operation
Type of work * a Part of the railway of Hail area. .
Cutting. * Filling - layers of sand. * Filling – layers of sub base
Supply of 750000 m3 sub base.
The duration of the contract is one year, 2008 AD
|
|
The main contractor Dammam Contracting company
Owner Al-Muhadib company
Type of work Supply of 250000 m3 sub base. 15
* Duration of the contract four months. * Filling layers. *
|
|
The main contractor Bin Ladin Group
Owner misery of high education
Type of work * Supply sub base for the project from
date of contract March, 2009.
|
|
The main contractor Bin Laden Group
Owner misery of high education
Type of work * Supply of materials.
* 5000000 m3 * supply sand 50000m3
* Digging 650000m3 and filling at the train stations.
|
|
project in Riyadh.
The main contractor
Francine Company
Owner misery of high education
Type of work
* Digging works for the bases of the train project at the university.
82800m3
|
|
The main contractor Sama Abha establishment
Owner Ben Talib
Type of work * Complete Infrastructure works. * 750.000m3
duration of contract 14 month
|
|
The main contractor Allatifia company
Owner : ministry of national guards
Type of work 365000m3
* Supply of materials with spread and pressing
date of contract (2009)
|
|
The main contractor Allatifia company
owner mrafiq company
Type of work establishing foundation
|
|
The main contractor Sama Abha establishment
owner minestry of education
Type of work establishing play ground
|
|
The main contractor Allatifia company
Owner : ministry of national guards
Type of work Supply of materials with spread and pressing
|
|
owner :
ministery of interior
main contractor:
El-seif Engineering Contracting CO
type of work
supply and install & compacting materials
amount
500,000 2m
|
|
The main contractor:
RAFAL Real Estate Devolopment Company
type of work
Structural construction for commercial building
Amount
20,000m2
|
|
|
|